Early appointment of O&M providers
Contents |
[edit] Introduction
On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider (Operation and Maintenance) is often appointed late in the project.
This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before practical completion (PC) gives the contractor, supply chain and O&M provider little time to manage the task properly. Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.
[edit] Issues with late engagement
- Added cost for O&Ms not previously budgeted for.
- Trades already left site and fully paid.
- No standardisation across O&M submissions.
- Increased pressure on site teams close to PC.
- Risk of missing or incomplete O&M submissions.
- Unhappy end client.
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.
O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.
The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.
[edit] Benefits of early engagement
- Cost certainty – a realistic budget for O&Ms in the cost plan.
- O&M templates in contract documents.
- Free up valuable site resource.
- Trades managed as and when they start on site.
- Plenty of time to conduct a thorough O&M review.
- Smooth, pain free handover at PC.
- Happy client with a complete and accurate as-built record.
Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as-built record at PC.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Heritage building skills and live-site training.
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.